Duke Energy Watery Dam Briefing
Duke Energy is undertaking an inflatable gate installation project at the Watery Hydro Station that requires a six to seven foot lake drawdown for 14 to 16 months of construction.
See it on the county map »
Council received a briefing on October 11, 2022; construction activities are scheduled to begin October 15, 2022. Watch for the next recap.
Follow Duke Energy Watery Dam Briefing
Get the recap whenever Council takes up Duke Energy Watery Dam Briefing - and every other
Kershaw County meeting. Free.
Every time the Recap has covered it
October 11, 2022
Discussed, no vote - Duke Energy Watery Dam Briefing: Duke Energy presented on the inflatable gate installation project at the Watery Hydro Station, which will require a six to seven foot drawdown of the lake starting October 15th to facilitate 14 to 16 months of construction. - COG Realignment: Council received an upd…